Since the unloading of the first LNG cargo ship and the start of a test run on April 1, CPC’s Guantang LNG Terminal has met its natural gas output target ahead of schedule on April 22. Since May 6, the TPC Datan Power Plant has consistently received 200 tons of natural gas per hour. On June 6, the test run was completed ahead of schedule, with a capacity of 900 tons of natural gas output per hour being tested. This progress was one week ahead of the original schedule, demonstrating CPC’s commitment to cooperating with the government’s domestic energy transition policy and collaborating to achieve the national gas supply goal.
According to CPC, the Guantang LNG Terminal’s current capacity has met the originally designed output capacity. To meet the natural gas demand of seven to nine turbine engines at the TPC Datan Power Plant and other users in the Northern region, the integration and optimization of various systems, as well as overall process reliability tests, will be carried out.